Staff
Christopher J. Gagne
N.C. P.L.S. L-4700
EDUCATION
Professional Land Surveyor Passed: October 26, 2007
Fundamentals of Land Surveying Exam Passed: April 17, 2004
Certificate# 1036 (MA)
Hazardous Waste June 7, 1999 - February 21, 2003
Operations Certified
Massachusetts College of Liberal Arts North Adams, MA
B.S. Physics May, 1998
Minor: Mathematics
AFFILIATIONS
North Carolina Socety of Surveyors-2008
Asheville Commericial Investors Realtors Association-2008
PROFESSIONAL SEMINARS
Dendrology-2008
Subdivision Law and Regulations-2008
Advanced Project Management-2007
Project management concepts and applications-2006
Staff Management-2006
ALTA/ACSM Surveys May 9, 2003
Land Court November 9, 2001
Advanced Data Collection September 22, 2000
Legal Aspects of Surveying August 18, 2000
Positional Tolerances Using Least Squares March 12, 1999
PRIOR PROJECT EXPERIENCE
Mountain Air Country Club
- Prepared cost estimates and time schedule for project.
- Maintained project billing and staff assignments for extensive topographic surveys and construction stakeout of multiple facets of development in 2006 and 2007.
- Performed and directed necessary field work to complete project.
Mountain Lifestyle Development Group Projects in Western North Carolina
- Directed survey team on three different projects totaling over 600 acres including topographic surveys, boundary surveys, subdivision platting, subdivision design, and client contact by phone, email, meetings, and trips to clients base of operations in Florida.
- Directed engineering staff on multiple associated design projects associated with client.
City of Asheville (Buncombe County, NC) 2007-2008 Water Replacement Line Replacement Project
- Water Line Replacement Phase
- Coordinated field and office staff towards achieving goal of completing an existing conditions topographic survey of 19,000+ linear feet of water line.
- Meet schedule criteria of project by completing project within one month.
- Coordinated with City of Asheville Water Department staff on achieving project goals including obtaining water as-built plans of existing utilities and coordination with utility location services.
- Pump Station Generator Phase
- Coordinated field and office staff towards achieving goal of completing an existing conditions topographic survey of twenty five pump station sites, boundary surveys of 41 pump station sites, and parcel acquisition plats for fifteen pump station sites.
- Coordinated with City of Asheville staff to develop schedules and deliverables.
- Assisted in bullet design drawings for twenty one pump station sites including generator placement and grading.
High Grove Subdivision Survey Services
- Led staff in completion of as-built survey including 16,000 linear feet of existing road network.
- Completed location and topographic survey for eighteen separate wetland areas including topographic mapping.
- Prepared revised easement plats for LPP sewer systems.
Tuckaseegee Road Way Design Topographic Survey
- Completed project under tight time frame that included over 40,000 linear feet of proposed road routing.
- Project included coordination with road construction contractor to facilitate road layout.
EEP and DENR Stream Restoration Projects
- Worked with MACTEC Asheville to complete stream monitoring projects for Brown Branch, Hanging Rock, Little Pine and Glade Creek, and Givens Estates (13,000 linear feet of stream total) throughout 2007 and 2008.
- Morgan Creek Construction stake out (8,800 linear feet) in McDowell County for Evironmental Banc & Exchange and designed by Kimley-Horn & Associates.